Weekly Plan
activeWeek 6 (May 13-17)
Task Progress
1 of 3 completed33%
Material Progress
Asphalt22t / 25t
Aggregate38t / 40t
Drainage Rock15t / 15t
Uploads
Photos1
Tickets1
Documents0
Construction Tasks
Track daily activities and progress
Complete roller section C shaping
Stage: sculpt
Planned: 25Actual: 2288%
Install drainage pipe zone 3
Stage: drainage
Planned: 40Actual: 40100%
Begin berm rough shaping
Stage: sculpt
Planned: 15Actual: 00
Material Targets
Track material delivery and usage
Asphalt22t / 25t
3.0t remaining88%
Aggregate38t / 40t
2.0t remaining95%
Drainage Rock15t / 15t
Target met100%
Site Staging Plan
Material storage, equipment, and access points
Recent Uploads
roller-section-progress.jpg
photosculpt
5/14/2024
aggregate-delivery-5421.pdf
ticket
5/13/2024
Add Quick Task
Week Notes