ProjectsRiverton Pump Track
Construction

Weekly Plan

active

Week 6 (May 13-17)

Task Progress
1 of 3 completed33%
Material Progress
Asphalt22t / 25t
Aggregate38t / 40t
Drainage Rock15t / 15t
Uploads
Photos1
Tickets1
Documents0
Construction Tasks
Track daily activities and progress

Complete roller section C shaping

Stage: sculpt

Planned: 25Actual: 2288%

Install drainage pipe zone 3

Stage: drainage

Planned: 40Actual: 40100%

Begin berm rough shaping

Stage: sculpt

Planned: 15Actual: 00
Material Targets
Track material delivery and usage
Asphalt22t / 25t
3.0t remaining88%
Aggregate38t / 40t
2.0t remaining95%
Drainage Rock15t / 15t
Target met100%
Site Staging Plan
Material storage, equipment, and access points
Recent Uploads

roller-section-progress.jpg

photosculpt

5/14/2024

aggregate-delivery-5421.pdf

ticket

5/13/2024